Nine key components for the high-speed rail rolling stock are undergoing testing at the "Ural Locomotives" plant in the Sverdlovsk region. The readiness of the site for locomotive production is 25%. This was announced by the Minister of Industry and Trade of the Russian Federation, Anton Alikhanov.
The construction of the plant is currently in an active phase, we need to build 67 thousand square meters by the beginning of the fourth quarter of next year, but despite the fact that construction is only underway, the overall readiness level is about 25%.
The certification of the trains is scheduled to be completed in March 2027. In the summer of 2027, they will be handed over to Russian Railways (RZD) for testing.
Nine main, most critical components are ready, undergoing testing, and about 30 more important components have already been pre-financed. "Sinara" has made the corresponding advances, and work is underway, we are not worried, we are on schedule so far.
The welding of the first seam of the first car body for the high-speed train has already begun at the "Ural Locomotives" plant.
Earlierwww1.ru reported that "Sinara"is modernizing "Lastochka" trains with Russian technological solutions.
Read related materials:
"Victory Lastochka" traveled between Moscow and St. Petersburg
Unmanned "Lastochka" put on rails
It became known when Russian Railways will receive new "Finist" trains
Now on home
Start of deliveries scheduled for 2027
Over 51,000 new motorcycles were sold in Russia in 2025
The car will take at least a year to assemble
The application's audience has reached 20 million users
The model will be included in the list of cars for taxis, price - from 2.25 million rubles
All parking lots of the "Administrator of the Moscow Parking Space" are connected to the service
The cars will be supplied to the Moscow Transport Service Directorate
Deliveries to India may begin in 2028
The technology provides automated search for all types of defects in power units
The plane flew 500 km, accelerating to 425 km/h
The plant stated that the information about the termination of purchases for models 6 and 8 is not true
Scientists are using the "Ekran-M" installation