Многострадальный Ту-214: названы главные причины задержек при строительстве самолёта

Among them are the delay in the technical re-equipment at KAZ and an acute shortage of labor

The production time of the revived Tu-214 aircraft at the Kazan Aviation Plant (KAZ, part of Tupolev JSC) has been repeatedly shifted "to the right", the local publication "Business Online" explained why.

Among the main reasons are the delay in the technical re-equipment of KAZ, the uneven purchase of components and materials, an acute shortage of labor hands and others.

On July 15, at a strategic session on the development of the aviation industry in Russia, Prime Minister Mikhail Mishustin instructed those responsible to determine the timing of the release of aircraft. First of all, the Prime Minister recalled the Tu-214, produced in Tatarstan.

At the same time, 400 million rubles have already been allocated from the federal budget for the modernization of the Tu-214. 400 million rubles were allocated. The funds were redistributed after the suspension of the Russian-Chinese project.

Earlier www1.ru reported that the Major General of Aviation called unrealistic plans to build 100 MS-21 aircraft by 2030

Read also materials:

"Tu-214 as it was not, so it will not be": what happened to the program of the Kazan liner

Russia has set a goal to double the production of Il-76MD-90A in 2.5 years

Il-114-300, Baikal and TVRS-44 not to wait: the legends of the USSR An-24 returned to Russian airlines

Now on home