Rosatom Starts Assembling Inner Containment Structure of Reactor Building at Leningrad NPP-2

The next stage of work is to supplement the frame with penetrations

Rosatom has started assembling the inner containment structure of the reactor building at the construction site of the third unit of Leningrad NPP-2. This was reported by the press service of the state corporation.

We have almost 2.5 years of intense work ahead of us. During this time, we need to erect a powerful prestressed reinforced concrete structure lined with steel, which will reliably shelter the reactor plant inside and maintain the tightness of the internal volume of the reactor building in all operating modes of the unit.
Vladimir Preguda, Director of Leningrad NPP

A special assembly platform with a height of 12 meters and a diameter of 44 meters was used in the construction. The immediate work will include welding 24 steel grades and supplementing the frame with penetrations and other elements.

Earlier, www1.ru reported that at Leningrad NPP-2, the foundation of the reactor shaft of the VVER-1200 power unit No. 3 was concreting.

Read materials on the topic:

Leningrad NPP-2 Begins Construction of Inner Containment Structure of Reactor Building

Working Ahead of Schedule: Concreting of the Foundation of the Safety Building Completed at Power Unit No. 4 of Leningrad NPP-2

The Tallest Structure in the Leningrad Region is Being Built at Leningrad NPP-2

Now on home