Названы главные проблемы с производством Ту-214: самолёт придётся перепроектировать

Kazan Aviation Plant Suffers from Shortage of Equipment and Personnel

Kazan Aviation Plant (KAZ, part of PJSC "Tupolev") will deliver only one Tu-214 out of the three planned in 2025. Inkazan reported on the problems the company is facing and why they cannot be solved overnight.

Tu-214
Tu-214

The Ministry of Industry and Trade last mentioned the Tu-214 back in September, talking about a forum for targeted students. In July, it was reported that the import-substituted aircraft was undergoing certification again, and it is unknown when it will be completed. Against the background of the successes of the MS-21 program, logical questions arise as to why the Tu-214 is not being built faster.

And there are several reasons: a shortage of personnel, a lack of production capacity, and the need to redesign the Tu-214.
Inkazan

Experts in the aviation industry have stated that in order to reach serious serial volumes, the production of the Tu-214 needs not just to be modernized, but actually redesigned. Only then can we talk about producing dozens of aircraft per year.

Earlier, www1.ru reported that a Rostec commission with Serdyukov and UAC visited the production of the PD-8 engine.

Read also:

"Birdie" Eyes: A New Profession "External Pilot" Has Appeared in Russia

The Manufacturer of Aircraft Engines PD-8, PD-14 and PD-35 Wanted to Be Bankrupted

MS-21 Certification Will Be Completed on Only Two Aircraft: No New Aircraft Will Appear

Sources
Inkazan

Now on home