Atommash specialists completed welding the upper semi- корпус of the reactor for the El-Dabaa NPP

Almost 3.5 tons of wire and 4.5 tons of flux were used for two circumferential welds

Workers at Atommash (part of Rosatom) have completed welding the upper semi- корпус of the reactor for the El-Dabaa NPP being built in Egypt, the state corporation's press service reported.

Upper semi- корпус of the reactor for the El-Dabaa NPP
Upper semi- корпус of the reactor for the El-Dabaa NPP

Almost 3.5 tons of wire and 4.5 tons of flux were used for two circumferential welds. It took 20 days to weld the semi- корпус for the second power unit.

The reactor корпус is a key piece of equipment at any NPP, and its reliability determines the service life of the station itself.
Viktor Orlov, General Director of NPO TsNIITMASH

Thanks to new metallurgical and welding technologies, the service life of reactors has been increased to 60-80 years (for generation 3+ reactors). In the future, the use of non-traditional materials will extend their service life to 100 years.

Read more on the topic:

Nuclear scientists have completed repairs at power unit No. 4 of the Beloyarsk NPP

Nuclear scientists have begun commissioning work at the pumping station of the first power unit of the Akkuyu NPP

"Safety Model": IAEA experts came to inspect the Novovoronezh NPP