The transport lock ensures the retention of radioactive substances in the containment zone
The equipment will be integrated into the electric pump units of the station's four power units
Workers integrated a thrust truss into an enlarged reinforcing block
Cairo is considering the construction of a small nuclear power plant
The containment consists of 12 "petal blocks"
State Corporation engineers poured the second tier of the inner containment shell in 24 hours
All work is on schedule
Welders used about 2 tons of flux and more than 1.5 tons of special wire
Likhachev: We Will Develop Cooperation with CIS and BRICS Countries
Nuclear scientists completed the work ahead of schedule
Almost 3.5 tons of wire and 4.5 tons of flux were used for two circumferential welds
The blocks are being installed by a heavy-lift crane with a lifting capacity of 1350 tons