Для МС-21 собрали всего 14 планеров: новые самолёты увидим нескоро

Another nine aircraft are at earlier stages of production

The Irkutsk Aviation Plant has assembled 14 MC-21 airframes, with a backlog of another nine aircraft at earlier stages of production. In Komsomolsk-on-Amur, 23 serial SJ-100 aircraft are in various stages of readiness, according to the head of the Ministry of Industry and Trade of the Russian Federation, Anton Alikhanov.

As domestic components are supplied and certification is completed, the aircraft will take to the skies and, after testing, be handed over to operators, he noted.

An updated comprehensive aviation industry development program will appear closer to the end of 2025. Accordingly, production plans will take into account the adopted adjustments.
Anton Alikhanov, Head of the Ministry of Industry and Trade

At the same time, Alikhanov confirmed that Russia intends to gradually increase the production of SJ-100 and MC-21 aircraft to 20 and 36 per year, respectively, after their certification is completed, with the possibility of further increasing production if there is demand.

Earlier, www1.ru reported that import-substituted parts for the SJ-100 will become cheaper, although they used to cost twice as much as those for Airbus.

Read more materials:

Metal Fatigue: Probable Cause of the Su-25 Attack Aircraft Crash Named

Full Cycle Production of PD-8 and PD-14 Blades Will Ensure Independence of Aircraft Engine Building in Russia

Airbus and Boeing Not Needed?: 200 MC-21 Aircraft Ready to Be Purchased by Russian Airlines

Sources
TASS

Now on home