Sinara – Transport Machines (STM), in collaboration with the Kalugaputmash plant, has improved the manufacturing process of PSS-2P snow removal trains. The assembly of the head and intermediate cars is now carried out in one workshop.
The stages of the production process were accelerated by the supply of components. Now they come from the machining production to the assembly, bypassing the warehouse. A special area was also created in the workshop to accommodate the workpiece for the next train.
Saving resources on logistics and supply has accelerated production threefold.
At the end of the first stage of the current machine, the released personnel begin work on the next one.
By the end of this year, it is planned to produce 3 PSS-2P snow removal trains. The machines were certified in 2022.
Earlier www1.ru reported that the first high-speed train will be equipped with autopilot.
Read more on the topic:
Hybrid of snowmobile and motorcycle: an innovative vehicle is being developed in Perm
Will replace foreign equipment: Sinara Group presented the Sinara-400 snow groomer project
Now on home
Герой России Гарнаев: никто из профессионалов о возобновлении производства на КАЗ всерьёз не говорит
Система отслеживает спутники на высотах до 50 000 км и ведёт за ними наблюдение
The armored vehicle is equipped with a KamAZ-740.35-400 diesel engine with a power of 400 hp.
Constant improvements in avionics, weapons and tactical capabilities will make the aircraft a flexible response to future challenges
The exterior of the KamAZ-54901 features fairings on the cab and chassis for fuel economy
Fighters are in demand both domestically and abroad
Tyazhpromexport and Venezuela Agree on Plant Revival
The company not only completed the state order, but also quickly mastered the production of AK-12K for special forces
Experts have developed a photogrammetric complex with a resolution of less than 1 cm