A new stage of work has begun in the construction of a complex for the production of high-speed trains in Verkhnyaya Pyshma — the installation of crane beams. This was reported in the press service of the Sinara Group holding.
These structures are designed to move goods in the horizontal and vertical planes. The building will be equipped with 11 overhead bridge cranes with a lifting capacity of 5 to 16 tons and a lifting height of all cranes up to 13 meters.
This object is the largest of those under construction: the length of the building is 420 meters, the width is 57 meters. The total area of the workshop exceeds 32 thousand square meters.
In total, the new complex will include five facilities. The first to be commissioned will be a test center with an area of more than 2 thousand km, which is planned to be completed in the spring of next year. The remaining buildings of the complex will be ready by December 2026.
Earlier www1.ru reported that tests of components for HSR were shown at a new stand.
Read more materials on the topic:
Now on home
Manturov: The funds will be used to build 50 passenger ships
Military personnel hone their skills to solve tactical tasks
Russians are traveling more often by train and car
На лайнеры установят российские двигатели ПД-8
Work continues on certification of MC-21-310 and Superjet-100
Rosimushchestvo and the Ministry of Finance of the Russian Federation are planning an open auction for the privatization of the facility
Experts advise explaining why services offer similar videos and show personalized advertising
The unique crystal could be auctioned off at a specialized auction
The negotiations concern the order of leasing payments, aircraft operation, and after-sales service
Belarus is interested in joint projects in aircraft construction, defense industry, and transport
Booking will be available through the app
The program until 2035 should involve the Belarusian industrial sector