Installation of the embedded part for the transport lock has begun at the second power unit of the El-Dabaa NPP in Egypt. This was reported by the press service of Rosatom State Corporation.
This part is a key element of the containment, to which the lock itself will be attached in the future. Important equipment (steam generators, the upper block of the reactor, main circulation pumps and pipelines of the primary circuit) will be delivered to the reactor building through it.
In the event of abnormal situations, the transport lock ensures the retention of radioactive substances in the containment, fire protection and, if necessary, the evacuation of personnel.
The work is being carried out in difficult conditions, since the embedded part is located between the third and fourth tiers of the internal protective shell. Installation requires high precision and clear coordination of actions of all participants in the process.
Earlier www1.ru reported that the Egyptian El-Dabaa NPP received more than 50 Russian asynchronous electric motors.
Read also materials on the topic:
- Reactor vessel for the first power unit of the El-Dabaa NPP delivered to the construction site in Egypt
- Rosatom will spend 11.2 billion rubles on climate technology for a nuclear power plant in Egypt
- Not only El-Dabaa: Rosatom may receive another contract for the construction of a nuclear power plant in Egypt