Installation of the 157-ton equipment took 8 hours
Preparations for the work took several months, using the experience of building previous power units
The equipment will undergo inspection and take its place in the VVER-1200 reactor shaft
The next stage of work is to supplement the frame with penetrations
Next stage is the installation of the reactor vessel
Russian State Corporation Offered the Most Favorable Conditions for Implementing the Nuclear Project
The foundations of all seven buildings of the "nuclear island" are planned to be prepared by December 2025
The cooling tower will cool the turbines of the new power unit No. 3
24 metal structures with a total weight of 156 tons will be produced for the lower tier
Next stage is the production of eight impulse safety devices