Installation took 12 hours
Installation took 12 hours
The structure, over 70 meters high, is capable of withstanding hurricanes, shock waves, earthquakes and external explosions
Preparations for the work took several months, using the experience of building previous power units
The equipment will be inspected and placed in the VVER-1200 reactor shaft
Next stage is the installation of the reactor vessel
The foundations of all seven buildings of the "nuclear island" are planned to be prepared by December 2025
The cooling tower will cool the turbines of the new power unit No. 3
24 metal structures with a total weight of 156 tons will be produced for the lower tier