DongFang Electric Corporation May Become the Supplier for the Third and Fourth Units of the Leningrad NPP-2
Installation took 12 hours
The structure, over 70 meters high, is capable of withstanding hurricanes, shock waves, earthquakes and external explosions
Installation of equipment weighing 157 tons took 8 hours
Preparations for the work took several months, using the experience of building previous power units
The equipment will be inspected and placed in the VVER-1200 reactor shaft
The next stage of work is to supplement the frame with penetrations
Next stage is the installation of the reactor vessel
Russian state corporation offered the most favorable conditions for the implementation of the nuclear project
The foundations of all seven buildings of the "nuclear island" are planned to be prepared by December 2025