At JSC "LOMO" of the Kalashnikov Concern, builders have begun zero-cycle work at the site of the future mechanical assembly building (MAB). The building, with an area of almost 19,000 m2 and a height of 22.5 m, will allow the enterprise to significantly increase output volumes of high-precision products and move to the next technological level.

Construction of the future mechanical assembly building
Construction of the future mechanical assembly building
Источник изображения: Kalashnikov Concern

The foundation is fully ready: all 549 piles have been driven. Work on the column pile caps is actively underway — 35 of 105 structures have been concreted. In parallel, excavation of the foundation pit and relocation of utility networks from the construction footprint have been completed by 82%. Every day, 110 people are working at the site and 27 pieces of equipment are in use.

Construction of the MAB
Construction of the MAB
Источник изображения: Kalashnikov Concern

Suppliers of metal structures have already begun manufacturing the building frame, which will make it possible to start installing the main load-bearing elements in the near future.

Construction is proceeding simultaneously in two directions: a new MAB is being erected and major renovation of existing premises is being carried out for the installation of modern equipment.