At the Ural Locomotives plant in Verkhnyaya Pyshma, the installation of the first metal frame structure of the body for commissioning electric trains has been completed. Simultaneously with the construction, a new production complex is being designed.
At the same time, supplier companies have begun manufacturing prototypes of components for the high-speed train. In general, the project is progressing in accordance with the approved schedule.
The new facility will include a complex for the production of high-speed trains, a body for the formation of body components, a traction drive test center, a design and administrative center.
The installation of temporary railway tracks, bored piles of the main frame and power floor has been fully completed at the site. The installation of sub-concrete under the foundations, pile caps, plinth beams is coming to an end, 125 columns out of 139 have been installed, over 3 thousand cubic meters of concrete have been poured. Engineering preparation and excavation of local soil are nearing completion.
The new production complex will allow to carry out:
- Combining wagons into a train with connection of communications.
- Simulating the operation of a locomotive in real conditions.
- High-voltage and low-voltage tests.
- Checking the tightness of inter-car passages.
- Monitoring the operation of water supply and sewerage systems of wagons.
Earlier www1.ru reported that a sample of a unique engine for the first high-speed train in Russia is fully ready.
Read materials on the topic:
Putin was shown a model of the Russian high-speed train: what is known about the HSR project
Now on home
The reason for indexation may be inflation, an increase in VAT, and rising production costs
The Ministry of Industry and Trade believes that the increase in the levy will not affect responsible manufacturers
The crew accelerated the aircraft to 580 km/h instead of the cruising speed of 450 km/h
Ship equipment comes to Russia from China at inflated prices
Almaz-Antey and the Belarusian Ministry of Defense signed a contract for equipment maintenance
The complex's computing resources allow for the competent distribution of targets between launchers
Among the spacecraft are Aist-2T No. 1 and No. 2
Deputy Prime Minister Novak announced a postponement of the deadlines, but confirmed the commitment to developing the sector
Design engineers without experience are promised salaries from 80 thousand rubles
Hard and dense shot ensures the destruction of the target from the first hit, regardless of the drone's body material
Almost all body elements are zinc-treated
SOGAZ lost the case in court against UEC-UMPO