ZAES line not restored due to substation damage
The power line itself has been repaired, but a key hub 100 km from the plant remains de-energized

The power line itself has been repaired, but a key hub 100 km from the plant remains de-energized

For three months, Europe's largest nuclear power plant relied on a single external source of electricity

Reserve diesel generators put on standby

Likhachev: About 2.6 thousand tons are located outside the reactors, another 500 tons are in the reactor units

The station is operating normally, radiation levels are normal

Director of ZNPP spoke about plans to restore the "Dneprovskaya" line

The backup power line is once again providing power for the station's own needs

Work is underway under a local ceasefire regime

Rosatom will continue to apply for licenses for the remaining three power units until the end of 2026

Specialists found no deficiencies in the plant's operation

Work on Power Unit No. 5 includes maintenance of key equipment

The plant is training personnel to put it into generation mode

Only the operating organization of the Russian Federation can be responsible for the operation of the station

The station's operation is supported by emergency diesel generators, but everything is currently under control