Ferry "Petropavlovsk" is 95.8% ready — delivery scheduled for 2026

Construction is delayed by sanctions and difficulties with equipment supplies, the contract has risen in price to 3.8 billion rubles

The cargo-passenger ferry of the CNF22 project "Petropavlovsk" is 95.8% ready. The vessel is scheduled to be handed over in 2026, according to the state customer's directorate.

According to shipbuilders, the current geopolitical situation and sanctions restrictions make it difficult to supply equipment, carry out commissioning and testing, which increases the construction time.

The contract for construction was concluded in August 2019; the initial cost was 3.1 billion rubles, and the planned delivery date was indicated in December 2021. The ferry was laid down in March 2020 (Butoma Plant).

According to the initial plan, launching was scheduled for October 2022, sea trials for February 2023, and delivery for July 2023. However, in August 2022, the contract price was increased to almost 3.8 billion rubles, and the deadlines were shifted. Mooring trials started in February 2025; the ferry was previously scheduled to be handed over in July 2025.

Read more on the topic:

Rosmorrechflot has denied plans to build new ferries in Crimea

OSK "Vympel" has prepared a project for a new generation river ferry

Ferries between Sakhalin and Japan are planned to be launched soon

Sources
PortNews

Now on home