The modernization of hydro unit No. 6 has been completed at the Votkinsk HPP in the Perm Territory — the penultimate of ten.
All equipment was replaced with more modern, powerful and energy-efficient equipment. The work was completed in record time — in 329 days instead of the standard 350. After testing, the unit's capacity will increase from 100 to 115 MW.
The planned modernization of the station started in 2017, when the first unit was replaced. Since then, one updated machine has been put into operation annually. After the completion of the project next year, the total capacity of the station will increase from 1020 to 1150 MW.
Votkinsk HPP is a hydroelectric power station located on the Kama River in the Perm Territory. It is part of the Volga-Kama cascade of HPPs and is the second stage of the cascade on the Kama.
Read materials on the topic:
Wind farms will be built and the Volzhskaya HPP will be modernized in the Volgograd region
Hydro unit No. 15 has been modernized: the capacity of the Saratov HPP has increased to 1475 MW
Now on home
The reason for indexation may be inflation, an increase in VAT, and rising production costs
The Ministry of Industry and Trade believes that the increase in the levy will not affect responsible manufacturers
Экипаж разогнал лайнер до 580 км/ч вместо крейсерских 450 км/ч
Ship equipment comes to Russia from China at inflated prices
Almaz-Antey and the Belarusian Ministry of Defense signed a contract for equipment maintenance
The complex's computing resources allow for the competent distribution of targets between launchers
Among the spacecraft are Aist-2T No. 1 and No. 2
Deputy Prime Minister Novak announced a postponement of the deadlines, but confirmed the commitment to developing the sector
Design engineers without experience are promised salaries from 80 thousand rubles
Hard and dense shot ensures the destruction of the target from the first hit, regardless of the drone's body material
Almost all body elements are zinc-treated
SOGAZ lost the case in court against UEC-UMPO