Kazan Aviation Plant to Deliver Only Two Aircraft Instead of 4

The Kazan Aviation Plant named after S.P. Gorbunov (KAZ, a branch of Tupolev PJSC) will not be able to produce four Tu-214 medium-range aircraft by the end of this year. The manufacturer is missing the updated delivery schedule due to a shortage of engineers.

Tu-214 Aircraft
Tu-214 Aircraft

The first version of the Comprehensive Program for the Development of the Civil Aviation Industry (KPGА) until 2030 stipulated the transfer of ten aircraft to customers by the beginning of 2025. However, the Kazan Aviation Plant (KAZ) was only able to complete two deliveries. Of these, one aircraft was restored, and the construction of the other aircraft began before 2022.

This year, the plant will complete only one aircraft (assembly started in 2024) and begin construction of the second aircraft. The main problem delaying production and deliveries is the shortage of engineers.

The Tu-214 medium-range airliner is a deep modernization of the Soviet Tu-204. Its production was established in 2022, when the world's largest civil aircraft manufacturers refused to cooperate with Russian airlines amid sanctions.

Earlier, www1.ru reported that Russia will significantly increase the production of Tu-214 in 2025.

Read more on the topic:

Another Il-96-400T jet took to the air: the first Russian commercial vessel certified in the USA

Rostec showed how parts for Il-96, Il-76, MS-21 and SJ-100 are strengthened

With a Russian engine: SJ-100 will perform about 200 test flights

Sources
Vedomosti

Now on home