S7 Group's "S7 Development Center" has suspended the construction of a plant for the development of parts for gas turbine engines in St. Petersburg. The new enterprise was to be located at the "Parnas" site.
It was assumed that the production would create 328 new jobs. The construction involved the appearance of an administrative building with an area of 1800 m² and a production complex with an area of 6100 m².
The construction would have cost approximately 7.5 billion rubles. The enterprise could have started operating in the second quarter of 2027. Currently, the construction has been postponed indefinitely.
The plant was to produce blades for the hot section of gas turbine engines, which are necessary for the completion of aircraft power plants. For example, up to 3000 parts are required to repair or create one engine.
Earlier www1.ru reported that KAZ concluded contracts for the supply of 23 Tu-214 passenger aircraft.
Read also:
Competitors for Airbus and Boeing: seven Russian aircraft are at the certification stage
Now on home
Hard and dense shot ensures the destruction of the target from the first hit, regardless of the drone's body material
Almost all body elements are zinc-treated
SOGAZ lost the case in court against UEC-UMPO
A rare SUV with a mileage of 38,533 km is offered for 2 million rubles
The government has included passenger and cargo airships among the key transport technologies of the future
Moscow sent 43 containers of weapons, including ATGMs and sniper rifles
There is a need to increase air traffic within Russia and abroad
Lada Niva Travel with a new 1.8-liter engine tested at temperatures of -25 and -30 °C
Производить первую энергию планировали ещё в апреле 2025 года
Retail is in second place, and education and medicine are in third place
The basic version of the system is capable of hitting targets at a range of up to 300 km
Security forces challenged the legality of yachting entertainment