Отечественная турбина «Ростеха» в составе ТЭС «Ударная» заработала на максимальную мощность

It is intended to replace imported units

The GTD-110M gas turbine, created to replace foreign units, has reached maximum capacity. It is used as part of the "Udarnaya" TPP in the Krasnodar region. It is manufactured by the United Engine Corporation (UEC), which is part of Rostec.

During the tests, the turbine operated for 72 hours at maximum load. No issues were identified in its operation. The capacity of the "Udarnaya" TPP reached 560 MW after the launch of the third power unit.

The commissioning of this thermal power plant will reduce the load on the power system of the Krasnodar region and the South of Russia. It will serve industrial enterprises in the region, the municipal sector, and housing.

It is planned that GTD-110M turbines will be installed instead of imported equipment at TPPs across the country.

Read more on the topic:

Russia Starts Producing New 170 MW Gas Turbines to Replace Imported Ones

New Complex for Assembling GTD-110M Gas Turbines to Be Built in Russia

First Domestic Gas Turbine Industrial Engine Being Tested in Russia

Sources
ODK

Now on home