Nuclear specialists have shut down power unit No. 2 with an EGP-6 reactor at the Bilibino NPP (Chukotka). It will switch to a mode without electricity generation, the Rosatom press service reported.

Bilibino NPP in Chukotka
Bilibino NPP in Chukotka
Источник изображения: Wikipedia/Creative Commons
The disconnection from the grid and cooling of the reactor units of the other two power units of the Bilibino NPP (No. 3 and No. 4) are scheduled for December 11 and 22.
Rosatom Press Service

Power unit No. 1 was shut down back in 2018. Specialists removed spent nuclear fuel (SNF) from the reactor core, moving it to a storage pool.

Subsequent stages of decommissioning the Bilibino NPP:

  • removal of SNF to the "Mayak" production association
  • removal of working fluids from equipment
  • retrofitting of the radioactive waste management system
  • decontamination of equipment
  • fragmentation of structures and buildings
  • rehabilitation of the NPP site

Andrey Kuznetsov, chief engineer of the Bilibino NPP, stated that there is a lot of work ahead. According to him,"the start of full rehabilitation of the site is seen beyond 2054".