The laying of railway tracks for the liquid bulk complex has been successfully completed at the "Favor" port, which is part of the "Port Alliance". Currently, work is underway to ballast, align, and straighten the tracks, according to the port's official channel.
In total, about 1.4 kilometers of railway track were laid, including: two tracks on the overpass for ammonia discharge, two dead-end tracks for wagon parking, three turnouts, and one connecting track for the passage of goods to the liquid bulk complex.
In addition, commissioning works are currently being carried out on the railway overpass for ammonia discharge. The technological pipeline has already been cleaned and is now being tested for strength, density, and tightness.
The launch of the new infrastructure will be possible after the facilities are put into permanent operation, which will allow the necessary documents to be signed with Russian Railways (JSC RZD) to organize the supply and removal of rolling stock on the constructed tracks.
Read more on the topic:
New complex for oil spill response developed in Russia
Vladivostok Sea Port Migrated to a Digital Twin: How It Works