Unigreen Energy has commissioned the Krasinskaya solar power plant (SES) with a capacity of 63 MW in the Lagansky district of Kalmykia. This was reported by the company's press service.
Krasinskaya SEC is equipped with more than 150 thousand double-sided solar modules of Russian production. Over 800 km of cable lines have been laid at the station.
The projected annual electricity generation is 99.6 million kWh. This will reduce carbon dioxide emissions by 35 thousand tons each year.
The SES uses a tracker system to track the sun. It increases electricity generation by 20-25% compared to modules with a fixed angle of inclination.
Krasinskaya SES became the fourth in the region. The republic also operates the Maloderbetovskaya SES (capacity 60 MW), the Yashkulskaya SES (capacity 58.5 MW), and the Arshanskaya SES (capacity 115.6 MW). After the start of the Krasinskaya SES, the capacity of power plants in Kalmykia reached 516.1 MW.
The company Unigreen Energy continues the construction of the Laganskaya solar power plant with a capacity of 63 MW. The new energy facility will be erected next to the Krasinskaya SES. The work is scheduled to be completed by the end of 2025.
Earlier www1.ru reported that the largest solar power plant in Russia will be built in Dagestan.