Ключевой компонент турбины: атомщики установили ротор низкого давления на АЭС «Аккую»

Rosatom: Work is underway on power unit No. 1

A key turbine component has been installed at the first power unit of the Akkuyu NPP, which is under construction in the Turkish province of Mersin. This is a low-pressure rotor, which weighs 255 tons, the Rosatom press service reported.

Akkuyu NPP
Akkuyu NPP

The last of the two rotors was installed using an overhead crane in the turbine building. According to Sergei Butskikh, CEO of Akkuyu Nuclear, the installation of the rotor is a technically complex operation that requires special precision.

All the main large-sized components of the turbine unit of Unit No. 1 of the Akkuyu NPP have been installed in the design position. 
Sergei Butskikh, CEO of «Akkuyu Nuclear»

Before testing the unit, the nuclear engineers will align the turbine shaft line and ensure the tightness of its secondary circuit.

Read also on the topic:

Nuclear engineers installed electric motors for reactor unit pumps at Akkuyu NPP

Crane of the German-Swiss company Liebherr lifted the dome of the outer containment shell of power unit No. 1 at the Akkuyu NPP

Turkey is preparing measures against Siemens due to delays in the supply of equipment for the Akkuyu NPP