Части «Сибирского кольцевого источника фотонов» прибыли на сборку

The first girders with booster synchrotron equipment have been delivered to the site

The stand test building (STB) of the "Siberian Ring Photon Source" (SKIF) has received the first girders with booster synchrotron equipment. The assembly of the world's most advanced synchrotron radiation source will begin soon. The injector will be ready by July 20, where power supplies, electronics, girders, and a linear accelerator can be moved.

The STB currently houses 25% of the booster synchrotron structure. It consists of girders with magnetic and vacuum equipment: dipole magnets, quadrupole and sextupole lenses, correctors, and vacuum chambers. The total weight of this equipment is more than 40 tons. The Budker Institute of Nuclear Physics SB RAS (BINP SB RAS) is the sole contractor for the complex of works on the manufacture, assembly, supply, and commissioning of the SKIF Shared Resource Center's accelerator complex equipment, including the booster synchrotron equipment.


A total of 44 booster synchrotron girders will be assembled in the injector building, forming a ring with a perimeter of 158 meters. The positional accuracy of the girder modules will be about 70 micrometers: this is the thickness of an adult's hair. In the booster synchrotron, the electron beam will be accelerated to 3 GeV in half a second. The SKIF Shared Resource Center operates at this energy.

Now on home