Туманное будущее СУГ-терминала «Ремсталя»: китайская Haiwei обещала вложить 7 млрд рублей, но российская компания начала банкротство

A representative of Remsstal stated that there is no threat to the project's implementation

The Arbitration Court of the Khabarovsk Territory has introduced a supervision procedure for Remsstal Company LLC, which is engaged in the construction of the first marine terminal for transshipment of liquefied petroleum gas (LPG) in the Far East. The decision was published in the file of arbitration cases. The procedure will last until December 17, 2025, and an arbitration manager has been appointed.

construction of the LPG terminal in the Far East
construction of the LPG terminal in the Far East

Remsstal is implementing a terminal project in Egge Bay of the Sea of Japan, where it is planned to receive, store, and ship propane, butane, and LPG mix. The capacity at the first stage was estimated at 1 million tons of products per year. Supplies are intended for countries in the Asia-Pacific region. The founder of the company is businessman Rifkat Badrutdinov.

In 2024, the head of the Russian Direct Investment Fund, Kirill Dmitriev, announced an agreement with China's Hebei Haiwei Group to invest 7 billion rubles in the project. The total construction cost was estimated at 30 billion rubles. In August of the same year, the United States added Remsstal to the sanctions list.

The initiator of the bankruptcy was ZAO Vostsibtransproekt, whose claims against the company amount to 28.5 million rubles, including debt and penalties. In addition, Badrutdinov's own structure — RC PT SDM Remsstal Company LLC — declared a debt of 195.7 million rubles, the petition has not yet been processed.

According to reports, in 2019 the company's revenue exceeded 100 million rubles, but in 2023 it amounted to only 10 thousand rubles. In 2024, the figure increased to 402 thousand rubles with a loss of 22.8 million rubles. The value of fixed assets at the end of the year was estimated at 6.1 billion rubles, net assets — at 4.9 billion rubles.

The company emphasizes that the terminal project is not closed. A representative of Remsstal told RBC that the situation is "absolutely controlled" and does not pose a threat to the project's implementation. Experts note that with the active participation of affiliated creditors, the debtor can maintain control over the procedure and emerge from the crisis.

Read materials on the topic:

The largest project in the gas industry in the world: construction of the Power of Siberia 2 gas pipeline has started

Half a billion cubic meters of gas per year: a floating LNG regasification station is being built in Kamchatka

LNG production will be established for export terminals in China in Primorye