JSC TVEL has completed the modernization of equipment for the production of low-enriched uranium at the plant in Zelenogorsk.
The fuel division of Rosatom State Corporation, JSC TVEL, has successfully completed a large-scale modernization of the main uranium enrichment equipment at the electrochemical plant in Zelenogorsk (Krasnoyarsk Territory). Work on the installation of modern 9+ generation gas centrifuges lasted six years.
The plant produces low-enriched uranium for nuclear power plant fuel assemblies, stable and radioactive isotopes, as well as other high-tech products. Most of the start-up stages were put into operation ahead of schedule.
The modernization is part of a program to upgrade the separation equipment of Rosatom's fuel division with a phased replacement of old centrifuges.
Read related materials:
Pilot operation of fifth-generation uranium-plutonium fuel has begun at the Novovoronezh NPP
Akkuyu NPP: ten interesting facts about the most modern and safe nuclear power plant
Now on home
Discounts in transport, pharmacies and stores will be able to be credited without applications as early as July 1, 2026
Now you can "be" anywhere - from meeting a star to a new appearance
Aircraft with tail number RA-96023 landed at Vnukovo Airport
NIITM and NIIME are creating an installation for sputtering aluminum onto 200 mm diameter wafers
PANDA has launched the production of specialized elevators for industry
The power plant remained in the dimensions of the AL-31F, but the thrust is 30% more powerful in afterburner
New observations show a more severe scenario
The height of the structure is 2.5 meters, and its total weight is 25 tons
The "Superjet" underwent special testing: approaches to landing with go-arounds were practiced, and the stall warning system was tested.
Internet speed may increase by 60%, and the connection may become more stable