Testing of systems and equipment at the first power unit of the Rooppur NPP was successful

The next step is hot testing of the reactor plant

Rosatom specialists conducted a series of tests of systems and equipment of the primary circuit of the Rooppur NPP, the state corporation's press service reported.

Rooppur NPP
Rooppur NPP

The check included several stages - filling the primary circuit with water, creating the necessary pressure and temperature, as well as preparing the main and related systems. An automated process control system was also put into operation (it provides control and monitoring of parameters during hydraulic tests).

This is a significant stage that brings us closer to the next important step - hot testing of the reactor plant. We are confident that the station will become a reliable source of energy for Bangladesh for decades to come.
Press service of Rosatom State Corporation

At the end, the specialists monitored the condition of the equipment and recorded all indicators in accordance with technological standards.

Earlierwww1.ru reported that Rosatomcompleted construction and installation works at the Rooppur NPP in Bangladesh.

Read materials on the topic:

Rosatom has supplied equipment for an automated radiation monitoring system for the Rooppur NPP

Start of commissioning works: simulators of heat-generating assemblies are loaded into the reactor at the Rooppur NPP in Bangladesh

The northernmost NPP in the world: two power units of the Floating Nuclear Power Plant "Akademik Lomonosov" were repaired in Chukotka

Now on home