Translated with AI from the Russian original.

The Rosatom State Corporation plans to complete the construction and prepare for commissioning a unique module for the creation of nuclear fuel (fabrication and refabrication module) in the city of Seversk (closed administrative-territorial entity, Tomsk Region) in 2024. The work is being carried out as part of the "Proryv" project.

The construction of an experimental demonstration power complex (ODEC) is underway at the site of the Siberian Chemical Combine. The module will operate on the basis of the future BREST-OD-300 reactor (a fast neutron installation with a lead-bismuth coolant).

Plans for 2024: completion of construction and preparation for commissioning of the nuclear fuel fabrication/refabrication module at the ODEC site.
Report of JSC Atomenergoprom

In 2023, specialists completed the concreting of the reactor shaft structures and the installation of the BREST support plate weighing 160 tons.

In the Tomsk Region, for the first time in world practice, a "fast" reactor and a closed nuclear fuel cycle technology will be introduced at one nuclear power plant site. Irradiated fuel, after processing, will be sent for refabrication. It is expected that the system will become independent of external supplies of resources for the nuclear reactor.

Earlier www1.ru reported that Rosatom is assembling the RITM-200N reactor.

Read related materials:

Russian cooling devices delivered to Seversk for the "reactor of the future"

Launch dates announced for the world's first lead-cooled reactor BREST-OD-300 - it was created in Russia

Russia and Belarus are working on a mobile nuclear power plant project

MEPhI specialists have found an alloy to extend the service life of a future thermonuclear reactor

Never miss our newsAdd this site to your preferred sources to see us more oftenAdd on Google

Now on the front page