FSUE "Rosmorport" has terminated the contract with the Onega Shipbuilding Plant for the construction of two auxiliary icebreakers worth 18.5 billion rubles. The contract was concluded in July 2021, and the termination agreement was signed on June 10.
Icebreakers with a capacity of 12-14 MW of the Icebreaker7 class were to operate in solid ice up to 1.5 m and use diesel fuel or liquefied natural gas - such vessels have not yet been built in Russia.
Initially, the Turkish shipyard Kuzey Star was supposed to perform the subcontract, but due to sanctions and problems with the supply of equipment, construction was not carried out. At the same time, Rosmorport had previously transferred an advance payment of 9.27 billion rubles to the Onega plant. The planned delivery dates of the vessels were postponed from 2024 to 2026.
The project involves the use of foreign components, including Azipod rudder propellers and Wartsila diesel generators, which now requires redesigning the vessels.
Read more on the topic:
The main distribution board has been installed on the nuclear icebreaker Chukotka
The icebreaker Arktika, built in 2020, has been sent for repairs
The newest nuclear icebreaker Yakutia has set off on its first voyage
Now on home
The service contains data on 45,000 fraudulent sites
Modernized engines may equip the Lada Azimut crossover
The price is 132 billion 265.8 million rubles
The manufacturer plans to strengthen its lineup of light commercial vehicles
The production of carbon fiber was organized in the shortest possible time
Electric vans will speed up the repair of urban transport infrastructure
Countries are working to synchronize regulations in the field of AI
The service's average daily audience is 55 million people
Stable Isomaterial Based on Metakaolin Has a Density Below 300 kg/m³
Re-identification quality improved twofold with new DynaMix method
Russians will be able to find out about debts online