Novosibirsk CHPP-3 dismantles 500 tons of metal for a new boiler with a capacity of 320 tons of steam per hour
After the upgrade, the station will increase its thermal capacity by 20%

After the upgrade, the station will increase its thermal capacity by 20%

Installation of the main equipment of unit No. 11 is planned to begin in October

Large-sized equipment was installed using two overhead cranes without stopping the plant's operation

Specialists will assess the equipment's condition after the first months of operation and continue modernizing the station's main units

New equipment will increase the station's capacity to 537 MW

Equipment modernization will increase the station's capacity by 40 MW

The plant continues to replace 65-year-old equipment with modern domestic turbines

A giant 170-ton stator was transported during the reconstruction of Unit No. 7

The upgrade boosted the plant by 70 megawatts and transitioned the power unit to digital control