Installation of control and management systems for the reactor plant has begun at Unit 1 of the Akkuyu NPP, which is under construction in Turkey (Mersin Province). The equipment was manufactured under the supervision of specialists from Rosatom Automated Control Systems JSC. This was reported by the press service of Rosatom State Corporation.

Akkuyu NPP
The reactor control and management system is the most important complex of technical means that receives and processes information from sensors located, among other places, in the reactor core.
Dmitry Dimashov, Technical Director of RASU ATCS Direction

According to him, the data obtained is processed by upper-level automation tools, providing NPP operators with information on the safe operation of the power unit.

Akkuyu NPP

According to the corporation's press service, the first 11 pieces of equipment have been installed in the reactor building. Next, the nuclear scientists will install a vertical stand necessary for commissioning works before the power unit is launched. The next stage is the installation of equipment for the executive part of the reactor control and protection system.

Read also on the topic:

Enriched Uranium for Brazil and Mexico: Rosatom State Corporation Expands Cooperation with Latin America

Rosatom State Corporation to Help Brazil Meet Nuclear Energy Needs

Russia's Second Major Project in Turkey: Rosatom State Corporation Plans to Build the Sinop NPP