Soviet turbine worked 58 years without pause at Saratov HPP: it is being replaced by a 10-meter giant

"RusHydro" will install a new PL 20-V-1030 unit

At the Saratov HPP (part of PAO "RusHydro"), modernization of hydro unit No. 18 has begun. This is the last hydro unit to be updated as part of a large-scale long-term project to replace the hydro turbines of the Saratov HPP.

Image source: Wikipedia

Specialists will replace the runner, runner chamber, cover and turbine shaft, guide apparatus, and other components.

The old Soviet turbine PL20/661-V-1030 from the Kharkov Turbine Plant operated for a record 58 years. It was put into operation in the late 1960s.

The historical equipment is being replaced by a completely domestic new-generation vertical Kaplan turbine – PL 20-V-1030, designed by engineers of the Russian plant AO "Tyazhmash".

The main uniqueness of the new machine lies in its dimensions – the diameter of the runner is 10.3 m. This is the largest unit of its type in Russia.