Подрядчик ВАСО сорвал сроки технического перевооружения цехов для Ил-112В, но избежал штрафа

Арбитражный суд Воронежа отказал во взыскании неустойки с подрядчика, задержавшего модернизацию для производства военно-транспортного самолёта

The Voronezh Arbitration Court refused PJSC "Ilyushin Aviation Complex" to recover more than 5 million rubles in penalties from the contractor for disrupting the deadlines for the technical re-equipment of the workshops of the Voronezh Aircraft Construction Company (VASO). The work was carried out in 2021-2022 as part of preparations for the serial production of the Il-112V military transport aircraft.

The first flight prototype of the Il-112V

According to the case materials, the contractor completed the modernization only in October 2023, although the deadlines were missed. However, the defendant pointed to delays in payment from the customer, which influenced the court's decision.

The Il-112V was developed as a light military transport aircraft to replace the outdated An-26. The first test flight in 2021 ended in disaster due to an engine malfunction, which led to the suspension of the project. The future of the Il-112V remains unclear - VASO does not provide official comments.

Read more on the topic:

GTLK Again in Court: New Claim for 19.7 Million Rubles Due to UAV Delivery Delays

Third Lawsuit Filed Against the Manufacturer of T-90M Tanks: MMK Increased Claims Against Uralvagonzavod to 105 Million

To Recover 668 Million Rubles: The Ministry of Defense Filed Five Lawsuits in Court Against the Military Construction Department