Rosatom completed construction and installation works at the Rooppur NPP in Bangladesh

Testing program launched at the first power unit

The staff of the Rooppur Nuclear Power Plant in Bangladesh (located 160 km from the city of Dhaka) has begun a testing program at the first power unit after the completion of construction and installation works. This was reported by the press service of the Rosatom State Corporation.

The company clarified that the first stage of the reactor plant's commissioning operation is currently underway. During this stage, specialists check the operability of equipment and mechanisms, as well as the main circulation pumps (MCP).

The program will culminate in testing the reactor plant at nominal parameters without nuclear fuel. This should confirm that the equipment meets all design specifications. After completing the entire set of tests, the unit will be ready to start commissioning operations.
Rosatom State Corporation

The commissioning of the Rooppur NPP will provide the Republic of Bangladesh with environmentally friendly and safe energy.

Read also:

Rosatom supplied automated radiation monitoring system equipment for the Rooppur NPP

Start of commissioning works: Rooppur NPP in Bangladesh is loading simulators of fuel assemblies into the reactor