Россия строит новый цех тяжелого машиностроения на 12 тысяч тонн продукции в год

It will produce equipment for the mining and metallurgical and machine-building industries

The "Mechanical Repair Complex" (part of the MMK group) in the Chelyabinsk region is preparing a site for a new production facility - a new heavy engineering workshop will appear there.

Heavy engineering accounts for an average of about 60% of the products of the machine-building complex. It is considered the leading industry of the entire country's industry<br>

The plant, the construction of which will cost 5 billion rubles, will produce material-intensive equipment for the mining and metallurgical and machine-building industries of Russia. These are:

● equipment for continuous casting machines;

● overhead cranes for metallurgical production;

● slag trucks with a lifting capacity of up to 500 tons;

● converters and support rings;

● steel-teeming and pig-iron ladles with a capacity of 50 to 350 tons;

● blast furnace shells;

● mixers and mixer trucks with a lifting capacity of 600 tons;

● rotary kilns and grinding mills;

● dump truck bodies with a lifting capacity of up to 225 tons.

In total, the workshop will be able to produce about 12 thousand tons of machine-building products per year, and they hope to launch production in it in the third quarter of 2025.